The links below contain guidelines for achieving each goal, including recommended processes for each design phase.
* Regional Priority (RP) credit for the following zip codes: 02134 (Allston, MA), 02138, 02139 (Cambridge, MA)
EA Prerequisite 1: Fundamental Commissioning of the Building Energy Systems
EAp1 ROADMAP
| Design Phase | Recommended Approach: Activities | Recommended Approach: Responsibilities |
|---|---|---|
| Pre-Design | To maximize effectiveness, employ a commissioning agent as early as possible (even during pre-design). Include sustainability in the RFP language and emphasize the project's sustainability goals during the interview process. A third-party agent is preferable for objectivity. Although it is also possible to employ a member of the selected design firm, as long as that person is not also responsible for the project's design. See the OPR and RFP Language section for model RFP language. | Owner/Client |
| Pre-Design | Create Owner's Project Requirements for CxA to use when reviewing designs. | Owner/Client |
| Pre-Design | Create a Basis of Design for CxA to use when reviewing designs. | MEP |
| Design Development | Create a Cx plan. See the LEED-NC Reference Guide for details. Include Cx requirements in specifications. | Commissioning Agent |
| Design Development | If a project is going to pursue further commissioning and apply for EAc2: Enhanced Commissioning, the Commissioning Agent should participate in a review at Design Development. Review and provide analysis and recommendations for the design. | Commissioning Agent |
| Construction Documents | Review and provide a report with recommendations on the proposed systems. | Commissioning Agent |
| Construction | Verify systems are functioning as designed, per Commissioning plan, including corrections log. Complete Commissioning report. | Commissioning Agent |
| Construction | Complete LEED Online Letter Template and provide submittal and audit requirements per EQp1 requirements. | Commissioning Agent |
| Construction | This credit is a Construction Submittal and should be submitted to the USGBC at the end of the project. | OFS |
| Occupancy | Review building systems and warranties of commissioined equipment within 10 months of building completion. | Commissioning Agent |
Design Intent and Sustainability Principles
Commissioning enhances energy performance by ensuring that mechanical systems, controls and electrical systems are properly installed and balanced. It also ensures that energy management systems are working properly and are tuned to perform according to the time of day or night, the season and the day of the week. Commissioning relates to several of the Harvard University Sustainability Principles. The first states that the university wants to “Demonstrat[e] institutional practices that promote sustainability, including measures to increase efficiency." Commissioning is an important way to ensure that a system designed to be efficient operates efficiently. Commissioning also relates to an important component of the second Sustainability Principle: “maintenance of the built environment." Commissioning is one aspect of proper maintenance of the university's properties. In order to “support long-term economic decision-making," a tenet of the fourth Sustainability Principle, numerous building managers and project managers have enlisted commissioning as a way to ensure full economic benefit of systems designed for energy efficiency.
Financial Considerations
Estimated costs for commissioning range from 0.4-3.8% of the project cost, depending on complexity of the mechanical systems, when commissioning is incorporated, and the time the Commissioning Authority spends on each task (Cox, Dorgan and Dorgan, "The Value of the Commissioning: Costs and Benefits" as referenced in LEED-NC Version 2.1 Reference Guide, page 113).
Both the Western Area Power Administration and the GSA's Public Building Service say that commissioned buildings cost 8-20% less to operate than uncommissioned buildings ("Building Commissioning for New Construction").
LEED Requirements
See updated Credit Interpretation Rulings issued by the U.S. Green Building Council.
LEED-CI Version 3
"The following commissioning process activities must be completed by the project team:
- Designate an individual as the commissioning authority (CxA) to lead, review and oversee the completion of the commissioning process activities.
* The CXA must have documented commissioning authority experience in at least 2 building projects.
* The individual serving as the CxA must be independent of the project's design and construction management, though the CxA may be an employee of any firms providing those services. The CxA may be a qualified employee or consultant of the owner.
* The CxA must report results, findings and recommendations directly to the owner.
* For projects smaller than 50,000 gross square feet, the CxA may be a qualified person on the design or construction teams who has the required experience. - The owner must document the owner's project requirements. The design team must develop the basis of design. The CxA must review these documents for clarity and completeness. The owner and design team must be responsible for updates to their respective documents.
- Develop and incorporate commissioning requirements into the construction documents.
- Develop and implement a commissioning plan.
- Verify the installation and performance of the systems to be commissioned.
- Complete a summary commissioning report.
Commissioned Systems
Commissioning process activities must be completed for the following energy-related systems at a minimum:
- Heating, ventilating, air conditioning and refrigeration (HVAC&R) systems (mechanical and passive) and associated controls.
- Lighting and daylighting controls
- Domestic hot water systems.
- Renewable energy systems (e.g. PV, wind, solar)."
- LEED 2009 for Commercial Interiors Rating System, page 26
LEED-CI Version 2.0
"The following commissioning process activities shall be completed by the commissioning team:
- Designate an individual as the Commissioning Authority to lead the commissioning process activities.
- This individual should not be directly responsible for project design or construction management.
- Clearly document the owner’s project requirements and the basis of design for the building’s energy related systems. Updates to these documents shall be made during design and construction by the design team.
- Develop and incorporate commissioning requirements into the construction documents.
- Develop and utilize a commissioning plan.
- Verify that the installation and performance of energy consuming systems meet the owner’s project requirements and basis of design.
- Complete a commissioning report.
Commissioned Systems:
The energy-related systems to be included in the commissioning process activities include as a minimum:
- Heating, ventilating, air conditioning and refrigeration (HVAC&R) systems (mechanical and passive) and associated controls
- Lighting controls, including day lighting
- Domestic hot water systems
- Renewable energy systems (PV, wind, solar, etc.)."
- LEED-CI Version 2.0 Reference Guide, page 117
LEED Submittals (Construction Submittal)
LEED-CI Version 3
- "Update the commissioning plan at milestones throughout the project. This should happen, at a minimum, during the design development phase, the construction documents phase, and just prior to the kick-off meeting with the general contractor.
- Prepare a systems list that indicates which systems have been included within the scope of enhanced commissioning.
- Obtain confirmation that the commissioning authority has documented experience on at least 2 building projects.
- Retain copies of the owner's project requirements, basis of design, commissioning specifications, commissioning report, and systems manual."
- LEED-CI Version 3 Reference Guide, page 131
(Complete descriptions of documentation requirements are on LEED-Online)
LEED-CI Version 2.0
- "Provide the LEED-CI Letter Template, signed by the commissioning authority and tenant, confirming that the commissioning requirements for the project's energy related systems have been successfully executed or will be provided under existing contract(s).
- Provide a narrative and diagrams indicating how the HVAC system works, what portions are shared with other tenants in the building, what was included in the project scope of work, and if improvements were made in conjunction with the project by others to any common building systems supplying the tenant area."
- LEED-CI Version 2.1 Reference Guide, page 117
Additional Resources
EA Prerequisite 2: Minimum Energy Performance
EAp2 ROADMAP
| Design Phase | Recommended Approach: Activities | Recommended Approach: Responsibilities |
|---|---|---|
| Pre-Design | Set minimum energy performance criteria goals, using LEED referenced standards as a guideline. | Client/Owner |
| Conceptual Design | Consider the extent to which the building can exceed ASHRAE/IESNA Standard 90.1-2007. Begin using energy modeling to evaluate design options. | MEP |
| Schematic/Design Development | Fine tune the energy model accordion to the 90.1-2007 Building Performance Rating Method (Appendix G). Applicable building components include building envelope, HVAC, service water heating, power, lighting, and other equipment. Demonstrate that the building meets or exceeds ASHRAE 90.1. See the Energy Modeling section for guidance. | MEP |
| Construction Documents | Review drawings and specifications to ensure minimum energy performance goals are being met. | Client Project Manager, MEP Engineers |
| Construction Documents | Complete LEED Online Letter Template and provide submittal requirements. | MEP |
| Construction Documents | This submittal is a Design Submittal and should be submitted to the USGBC after Construction Documents are complete. | OFS or LEED Consultant |
Design Intent and Sustainability Principles
All Harvard buildings meet this prerequisite as they must comply with the Massachusetts Building Code. The goal is for the building to perform beyond what the code requires, to optimize energy performance. As stated in the first of the Sustainability Principles, Harvard University is committed to "Demonstrating institutional practices that promote sustainability, including measures to increase efficiency and use of renewable resources, and to decrease production of waste...both in Harvard's own operations and in those of its suppliers." This design element requires buildings to operate efficiently. It is particularly important to have effective use of energy at the user-end (lighting, heating, cooling), because efficiencies in these areas have a large impact on upstream energy production and result in significant savings.
Financial Considerations
There should be no added cost, as the minimum requirements will be met with the Massachusetts Building Code.
LEED Requirements
See updated Credit Interpretation Rulings issued by the U.S. Green Building Council.
LEED-CI Version 3
Design portions of the building as covered by the tenant's scope of work to comply with ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without addenda1), and complete the following:
- Comply with the mandatory provisions (Sections 5.4, 6.4, 7.4, 8.4, 9.4 and 10.4) of ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without addenda1).
- Achieve the prescriptive requirements (Sections 5.5,6.5, 7.5 and 9.5) or performance requirements (Section 11) of ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without addenda1).
- Reduce connected lighting power density 10% below that allowed by ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without addenda1) using either the Space-by-Space Method or by applying the whole building lighting power allowance to the entire tenant space.<
- Install ENERGY STAR qualified equipment for 50% (by rated-power) of ENERGY STAR eligible equipment2 installed as part of the tenant's scope of work. This requirement includes appliances, office equipment, electronics, and commercial food service equipment. Excluded are heating, ventilating and air conditioning (HVAC), lighting, and building envelope products.
Projects in California may use Title 24-2005, Part 6 in place of ANSI/ASHRAE/IESNA Standard 90.1-2007.
1Project teams wishing to use ASHRAE approved addenda for the purposes of this credit may do so at their discretion. Addenda must be applied consistently across all LEED credits.
- LEED 2009 for Commercial Interiors Rating System, page 15
LEED-CI Version 2.0
"Design portions of the building as covered by the tenant’s scope of work to comply with ASHRAE/IESNA Standard 90.1-2004 or the local energy code, whichever is more stringent."
- LEED-CI Version 2.0 Reference Guide, page 131
LEED Submittals (Design Submittal)
LEED-CI Version 3
- "For ASHRAE compliance, list any addenda used, and retain copies of ASHRAE compliance forms.
- If the project is using the prescriptive compliance path, assemble documentation demonstrating that the project meets all applicable requirements.
- For lighting power density reduction, refer to the Documentation Guidance section in EA Credit 1.1.
- For ENERGY STAR equipment, refer to the Documentation Guidance section in EA Credit 1.4."
- LEED-CI Version 3 Reference Guide, page 142
(Complete descriptions of documentation requirements are on LEED-Online)
LEED-CI Version 2.0
- "Provide the LEED-CI Letter Template, signed by the licensed professional engineer, architect or other responsible party, stating that the tenant space complies with ASHRAE/IESNA 90.1-2004 or local energy codes, whichever is more stringent. If local energy codes were applied, demonstrate that the local energy code is more stringent than ASHRAE/IESNA 90.1-2004.
California Title 24 2001 has been deemed to be more stringent than ASHRAE 90.1-2004 for LEED purposes. No demonstration of equivalency is required for project teams implementing Title 24 2001."
- LEED-CI Version 2.0 Reference Guide, page 131
Additional Resources
EA Prerequisite 3: Fundamental Refrigerant Management
EAp3 ROADMAP
| Design Phase | Recommended Approach: Activities | Recommended Approach: Responsibilities |
|---|---|---|
| Schematic Design | Minimize the need for halon fire suppressants and identify the best possible CFC- free refrigerants. | MEP Engineers |
| Design Development | Select equipment that does not contain halons. | MEP Engineers |
| Construction Documents | Complete LEED Online Letter Template and provide submittal requirements. | MEP Engineers |
| Construction Documents | This credit is a Design Submittal and should be submitted to the USGBC after Construction Documents are complete. | OFS or LEED consultant |
Design Intent and Sustainability Principles
According to the National Oceanic and Atmospheric Administration, "dramatic increases in concentration of chlorine and bromine in the stratosphere since the 1950s have brought about enhanced ozone destruction." In recent years, the total amount of bromine and chlorine in the stratosphere has decreased a few percentage points, thanks to many nations' adherence to the Montreal Protocol. According to the first of the Sustainability Principles, Harvard University is committed to continuous improvement in "demonstrating institutional practices that ...decrease production of ...hazardous materials, both in Harvard's own operations and in those of its suppliers." Eliminating CFCs has been essential in decreasing bromines and halons in the atmosphere. Monitoring the chemicals in the university's HVAC&R systems is part of the process indicated in the sixth Sustainability Principle, that the university is committed to continuous improvement in "Establishing indicators for sustainability that will enable monitoring, reporting and continuous improvement." Continuous learning is an essential component of the principles, and the application on-campus of ideas learned in the classroom, such as the research on ozone performed by the Division of Engineering and Applied Sciences, is a sustainable direction for the campus.
Financial Considerations
With careful planning, eliminating halon fire suppressants and choosing the best possible refrigerants should add minimal cost, if any.
LEED Requirements
See updated Credit Interpretation Rulings issued by the U.S. Green Building Council.
LEED-CI Version 3
"Zero use of chlorofluorocarbon (CFC)-based refrigerants in tenant heating, ventilating, air conditioning and refrigeration (HVAC&R) systems used within the LEED project scope of work."
- LEED 2009 for Commercial Interiors Rating System, page 16
LEED-CI Version 2.0
"Zero use of CFC-based refrigerants in tenant HVAC&R systems within the LEED-CI project scope of work."
- LEED-CI Version 2.0 Reference Guide, page 139
LEED Submittals (Design Submittal)
LEED-CI Version 3
- "Assemble manufacturers' documentation demonstrating the type of refrigerant used by the HVAC&R systems installed within the scope of the LEED project."
- LEED-CI Version 3 Reference Guide, page 149
(Complete descriptions of documentation requirements are on LEED-Online)
LEED-CI Version 2.0
"Provide the LEED-CI Letter Template, signed by a professional engineer or other responsible party, declaring that there are no CFCs in HVAC&R systems that have been installed or renovated within the LEED-CI project scope."
- LEED-CI Version 2.0 Reference Guide, page 139
Additional Resources
EAc1.1: Optimize Energy Performance - Lighting Power *
EAc1.1 ROADMAP
| Design Phase | Recommended Approach: Activities | Recommended Approach: Responsibilities |
|---|---|---|
| Budget Planning | ||
| Conceptual Design | ||
| Schematic Design | ||
| Design Development | ||
| Construction Documents |
Design Intent and Sustainability Principles
Financial Considerations
LEED Requirements
See updated Credit Interpretation Rulings issued by the U.S. Green Building Council.
LEED-CI Version 3
"Reduce connected lighting power density below that allowed by ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without addenda1) using either the space-by-space method or by applying the whole building lighting power allowance to the entire tenant space.
The points earned for reducing lighting power density below the standard are as follows:
Lighting Power Density Reduction below the Standard |
Points |
|---|---|
15% |
1 |
20% |
2 |
25% |
3 |
30% |
4 |
35% |
5 |
Project teams in California may use Title 24-2005, Part 6 in place of ANSI/ASHRAE/IESNA Standard 90.1-2007.
1Project teams wishing to use ASHRAE approved addenda for the purposes of this prerequisite may do so at their discretion. Addenda must be applied consistently across all LEED credits."
- LEED 2009 for Commercial Interiors Rating System, page 17
LEED-CI Version 2.0
*All projects registered after June 26, 2007 must achieve at least two EAc1 credits. These can be earned in any of the four sub-categories (EAc1.1, EAc1.2, EAc1.3, EAc1.4). This will improve the energy performance of all LEED certified green buildings by 14% for new construction and 7% for existing buildings.*
"Reduce connected lighting power density below that allowed by ASHRAE/IESNA Standard 90.1-2001 (with all addenda)* using either the space-by-space method or by applying the whole building lighting power allowance to the entire tenant space.
Option A. Reduce lighting power density to 15% below the standard (1 point)
OR
Option B. Reduce lighting power density to 25% below the standard, (2 points)
OR
Option C. Reduce lighting power density to 35% below the standard. (3 points)
*ASHRAE/IESNA 90.1-2004 will become the referenced standard once available."
- LEED-CI Version 2.0 Reference Guide page 143
LEED Submittals (Design Submittal)
LEED-CI Version 3
- "For ASHRAE compliance, list any addenda used.
- Assemble lighting compliance documents from the ASHRAE 90.1-2007 user's manual.
- List the rated power of installed lighting systems.
- List building area types or space area types with their corresponding gross floor areas.
- Assemble information about additional lighting power allowances and document that the allowances apply only to lighting systems that are separate from general lighting."
- LEED-CI Version 3 Reference Guide, page 157
(Complete descriptions of documentation requirements are on LEED-Online)
LEED-CI Version 2.0
- "Provide the LEED-CI Letter Template, signed by the professional engineer or other responsible party, stating that the lighting power density is reduced below ASHRAE requirements consistent with the level of credit being sought. AND
- Complete the Lighting Compliance Documentation provided in the ASHRAE/IESNA Standard 90.1 User’s Manual. Provide a separate calculation that shows the percentage reduction in lighting power."
- LEED-CI Version 2.0 Reference Guide page 145
Additional Resources
EAc1.2 Optimize Energy Performance, Lighting Controls
EAc1.2 ROADMAP
| Design Phase | Recommended Approach: Activities | Recommended Approach: Responsibilities |
|---|---|---|
| Budget Planning/CAPS | ||
| Schematic Design | ||
| Construction Documents | ||
| Construction Documents | ||
| Occupancy |
Design Intent and Sustainability Principles
Financial Considerations
LEED Requirements
See updated Credit Interpretation Rulings issued by the U.S. Green Building Council.
LEED-CI Version 3
"Design the project to include 1 or more of the following independent strategies:
- Daylight controls for daylit areas: (1 point)
Install daylight responsive controls in all regularly occupied daylit spaces within 15 feet of windows and under skylights. Daylight controls must switch or dim electric lights in response to the presence or absence of daylight illumination in the space.1 - Daylight controls for 50% of the lighting load: (1 point)
Install daylight responsive controls for 50% or more of the connected lighting load and demonstrate that 50% of the connected lighting load is daylight responsive. Daylight controls must switch or dim electric lights in response to the presence or absence of daylight illumination in the space.2 - Occupancy sensors: (1 point)
Install occupancy sensors for 75% of the connected lighting load.
1 American Society of Heating, Refrigerating, and Air-Condltioning Engineers. ANSI/ASHRAE/IESNA Standard 90.1 - 2007 90.1 User's Manual. (Atlanta, 2008). P.9-3
2 Ibid"
- LEED 2009 for Commercial Interiors Rating System, page 18
LEED-CI Version 2.0
*All projects registered after 6/26/07 must achieve at least two EAc1 credits. These can be earned in any of the four sub-categories (EAc1.1, EAc1.2, EAc1.3, EAc1.4). This will improve the energy performance of all LEED certified green buildings by 14% for new construction and 7% for existing buildings.*
"Install daylight responsive controls in all regularly occupied spaces within 15 feet of windows and under skylights."
- LEED-CI Version 2.0 Reference Guide page 149
LEED Submittals (Construction Submittal)
LEED-CI Version 3
- "Highlight daylit zones on interior lighting plans; indicate which luminaries correspond to each controller."
- LEED-CI Version 3 Reference Guide, page 162
(Complete descriptions of documentation requirements are on LEED-Online)
LEED-CI Version 2.0
- "Provide the LEED-CI Letter Template, signed by the professional engineer or other responsible party, stating that lighting controls were installed consistent with the credit requirement. AND
- Provide a narrative describing the lighting controls that have been incorporated in the tenant space design. Include a plan of lighting control zones showing each control device and lighting equipment controlled. Provide a schedule of lighting controls showing model, type and other characteristics."
- LEED-CI Version 2.0 Reference Guide page 149
Additional Resources
EAc1.3 Optimize Energy Performance, HVAC *
EAc1.3 ROADMAP
| Design Phase | Recommended Approach: Activities | Recommended Approach: Responsibilities |
|---|---|---|
| Budget Planning | Establish commitment/requirement to make decisions based on Life Cycle Costing, which connects capital costs of construction with the operations budget. | Owner/Client with CAPS |
| Budget Planning | Consider creating a financial incentive for meeting high performance building goals. (EPAct 2005 allows design teams to claim tax credits for energy efficient buildings.) | Owner/Client |
| Conceptual Design | Design charrette: identify energy operation goals for the design team. See examples of EAc1 submittals for energy savings other Harvard projects have achieved. Review EAc1 requirements. Identify opportunities for integrated design. Optimize energy loads through architectural element design and right-sizing of mechanical systems. | Owner, Project Manager, Architect, Engineer, OFS or other sustainability consultant. |
| Conceptual Design | Establish processes, methods and responsibilities for establishing and integrating LCC and building simulation. | Owner/Client and Project Manager with Project Team |
| Conceptual Design | Consider precipitation, wind and solar exposure of site to determine possible passive strategies. | Architect |
| Conceptual Design | Conduct energy modeling study. Use ASHRAE 90.1-2007 Appendix G (Building Performance Rating Method) to establish base cases. Model design case on proposed design. Optimize building performance using the model to evaluate decisions. See the Energy Modeling section for detailed guidance. | MEP |
| Schematic Design | Perform LCC study for proposed systems. | Architect |
| Schematic Design | Identify Green Campus loan fund and utility rebate opportunities based on LCC results. | OFS and Project Manager |
| Design Development | Review DD mechanical and architectural decisions based on LCC and energy model. | Architect, MEP |
| Construction Documents | Review CD mechanical and architectural decisions based on LCC and energy model. | Architect, MEP |
| Construction Documents | Complete LEED Online Letter Template and provide submittal requirements. | MEP |
| Construction Documents | This is a Design Submittal and should be submitted to the USGBC after Construction Documents are complete. | OFS or LEED Consultant |
Design Intent and Sustainability Principles
Financial Considerations
LEED Requirements
See updated Credit Interpretation Rulings issued by the U.S. Green Building Council.
LEED-CI Version 3
"OPTION 1
Implement 1 or both of the following strategies:
- Equipment Efficiency --(5 points)
Install heating, ventilation and air conditioning (HVAC) systems that comply with the efficiency requirements outlined in the New Building Institute's Advanced Buildings Core Performance Guide Sections 1.4: Mechanical System Design, 2.9: Mechanical Equipment Efficiency and 3.10: Variable Speed Control. - Appropriate Zoning and Controls: (5 points)
Zone tenant fit out spaces to meet the following requirements:
* Every solar exposure must have a separate control zone.
* Interior spaces must be separately zoned.
* Private offices and special occupancies (conference rooms, kitchens, etc.) must have active controls capable of sensing space use and modulating the HVAC system in response to space demand.
OR
OPTION 2
Reduce design energy cost compared with the energy cost budget for regulated energy components described in
the requirements of ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without addenda1)
AND
PATH 1 (5 points)
Demonstrate that HVAC system component performance criteria used for tenant space are 15% better than a system in minimum compliance with ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without addenda1).
OR
PATH 2 (10 points)
Demonstrate that HVAC system component performance criteria used for tenant space are 30% better than a system in minimum compliance with ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without addenda1).
1 Project teams wishing to use ASHRAE approved addenda for the purposes of this credit may do so at their discretion. Addenda must be applied consistently across all LEED credits."
- LEED 2009 for Commercial Interiors Rating System, page 19
LEED-CI Version 2.0
*All projects registered after 6/26/07 must achieve at least two EAc1 credits. These can be earned in any of the four sub-categories (EAc1.1, EAc1.2, EAc1.3, EAc1.4). This will improve the energy performance of all LEED certified green buildings by 14% for new construction and 7% for existing buildings.*
"OPTION A
Implement one or both of the following strategies:
- Equipment Efficiency: (1 point)
Install HVAC systems which comply with the efficiency requirements outlined in the New Buildings Institute, Inc.’s publication “Advanced Buildings: Energy Benchmark for High Performance Buildings (E-Benchmark)” prescriptive criteria for mechanical equipment efficiency requirements, sections 2.4 (less ASHRAE standard 55), 2.5, and 2.6.
- Appropriate Zoning and Controls: (1 point)
Zone tenant fit out of spaces to meet the following requirements:
* Every Solar Exposure must have a separate control zone
* Interior spaces must be separately zoned
* Private offices and specialty occupancies (conference rooms, kitchens, etc.) must have active controls capable of sensing space use and modulating HVAC system in response to space demand
OPTION B
Reduce design energy cost compared to the energy cost budget for regulated energy components described in the requirements of ASHRAE/IESNA Standard 90.1- 2001 (with all addenda)*.
- Demonstrate that HVAC system component performance criteria used for tenant space are 15% better than a system that is in minimum compliance with ASHRAE/IESNA Standard 90.1-2001 (with all addenda)*. (1 point) OR
- Demonstrate that HVAC system component performance criteria used for tenant space are 30% better than a system that is in minimum compliance with ASHRAE/IESNA Standard 90.1-2001 (with all addenda)*. (2 points)
*ASHRAE/IESNA 90.1-2004 will become the referenced standard once available."
- LEED-CI Version 2.0 Reference Guide, page 152
LEED Submittals (Design Submittal)
LEED-CI Version 3
- "List locations and functions of HVAC system automatic controls or sensors.
- Document potential energy savings per control and rasons for zone distribution.
- For cost-budget compliance, list the proposed design energy by end use, associated peak demand, and cost. Additionally, list baseline costs by energy type."
- LEED-CI Version 3 Reference Guide, page 172
(Complete descriptions of documentation requirements are on LEED-Online)
LEED-CI Version 2.0
- "Provide the LEED-CI Letter Template, signed by the licensed professional engineer or architect, stating that the HVAC system energy consumption is 15% or 30% (depending on credit taken) lower than a base case system defined in ASHRAE/IESNA Standard 90.1-2001, Section 11. (ASHRAE/IESNA 90.1-2004 will become the referenced standard once available.)
- Provide a completed copy of the Energy Cost Budget (ECB) Compliance Form. Provide a narrative description of the HVAC system serving the tenant space as well as a description of the building-level system. Plans and specifications should have an HVAC equipment schedule and plans showing the equipment within the space."
- LEED-CI Version 2.0 Reference Guide, page 152
Additional Resources
EAc1.4 Optimize Energy Performance - Equipment and Appliances
EAc1.4 ROADMAP
| Design Phase | Recommended Approach: Activities | Recommended Approach: Responsibilities |
|---|---|---|
| Budget Planning/CAPS | ||
| Schematic Design | ||
| Construction Documents | ||
| Construction Documents | ||
| Occupancy |
Design Intent and Sustainability Principles
Financial Considerations
LEED Requirements
See updated Credit Interpretation Rulings issued by the U.S. Green Building Council.
LEED-CI Version 3
"OPTION 1
Implement 1 or both of the following strategies:
- Equipment Efficiency --(5 points)
Install heating, ventilation and air conditioning (HVAC) systems that comply with the efficiency requirements outlined in the New Building Institute's Advanced Buildings Core Performance Guide Sections 1.4: Mechanical System Design, 2.9: Mechanical Equipment Efficiency and 3.10:Variable Speed Control. - Appropriate Zoning and Controls: (5 points)
Zone tenant fit out of spaces to meet the following requirements:
* Every solar exposure must have a separate control zone.
* Interior spaces must be separately zoned.
* Private offices and special occupancies (conference rooms, kitchens, etc.) must have active controls capable of sensing space use and modulating the HVAC system in response to space demand.
OR
OPTION 2
Reduce design energy cost compared with the energy cost budget for regulated energy components described in
the requirements of ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without addenda1)
AND
PATH 1 (5 points)
Demonstrate that HVAC system component performance criteria used for tenant space are 15% better than a system in minimum compliance with ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without addenda1).
OR
PATH 2 (10 points)
Demonstrate that HVAC system component performance criteria used for tenant space are 30% better than a system that is in minimum compliance with ANSI/ASHRAE/IESNA Standard 90.1-2007 (with errata but without addenda1).
1Project teams wishing to use ASHRAE approved addenda for the purposes of this credit may do so at their discretion. Addenda must be applied consistently across all LEED credits."
- LEED 2009 for Commercial Interiors Rating System, page 19
LEED-CI Version 2.0
*All projects registered after 6/26/07 must achieve at lest two EAc1 credits. These can be earned in any of the four sub-categories (EAc1.1, EAc1.2, EAc1.3, EAc1.4). This will improve the energy performance of all LEED certified green buildings by 14% for new construction and 7% for existing buildings.*
"For all ENERGYSTAR-eligible equipment and appliances installed in the project, including appliances, office equipment, electronics, and commercial food service equipment (but excluding HVAC, lighting, and building envelope products):
- 70%, by rated-power, of ENERGYSTAR-eligible equipment and appliances shall be ENERGYSTAR-rated (1 point); OR
- 90%, by rated-power, of ENERGYSTAR-eligible equipment and appliances shall be ENERGYSTAR-rated (2 points)."
- LEED-CI Version 2.0 Reference Guide, page 168
LEED Submittals
LEED-CI Version 3
- "List locations and functions of HVAC system automatic controls or sensors.
- Document potential energy savings per control and reasons for zone distribution.
- For cost-budget compliance, list the proposed design energy by end use, associated peak demand, and cost. Additionally, list baseline cost by energy type."
- LEED-CI Version 3 Reference Guide, page 172
(Complete descriptions of documentation requirements are on LEED-Online)
LEED-CI Version 2.0
- "Provide the LEED-CI Letter Template, signed by the responsible party, declaring that ENERGYSTAR-eligible equipment and appliances are ENERGYSTAR-rated and yield the indicated percentage of the total, determined by rated-power.
- Provide a narrative describing the equipment and appliances that will be installed in the project. Complete the schedule of equipment listing the types and quantity of equipment and appliances to be installed in the project along with the rated-power (or rated fuel input for commercial cooking equipment) of each type of EnergyStar eligible equipment and appliance. Indicate which equipment and appliances are ENERGYSTAR-rated. Indicate the overall percentage of equipment and appliances, based on rated electrical power (as well as rated fuel input for commercial cooking equipment), that is ENERGYSTAR-rated."
- LEED-CI Version 2.0 Reference Guide, page 168
Additional Resources
EAc2: Enhanced Commissioning
EAc2 ROADMAP
| Design Phase | Recommended Approach: Activities | Recommended Approach: Responsibilities |
|---|---|---|
| Pre-Design | To maximize effectiveness, employ a commissioning agent as early as possible. Include sustainability and LEED requirements in RFP language and emphasize the project's sustainability goals during the interview process. | Client/Owner |
| Pre-Design | Create Owner's Project Requirements for CxA to use when reviewing designs. | Client/Owner |
| Pre-Design | Create Basis of Design for CxA to use when reviewing designs. | MEP |
| Design Development | It is very important that the Commissioning Agent be brought in at design development to review documents at that stage if a project wants to achieve LEED-NC EA credit 3. However, at 90 Mount Auburn Street, the CA was brought in right after design development. The project team submitted a CIR, and was given approval as long as the Owner was committed to incorporate the recommended changes, even if they might constitute change orders. | Client Project Manager |
| Design Development | CxA must review and comment on DD documents. | Commissioning Agent |
| Design Development | Engineer must respond to comments from CxA on DD documents. | MEP |
| Construction Documents | CxA must review and comment on CD documents. | Commissioning Agent |
| Construction Documents | Engineer must respond to comments from CxA on CD documents. | MEP |
| Construction | Complete LEED Online Letter Template and provide submittal requirements. | Commissioning Agent |
| Construction | Develop systems manual for commissioned systems that provides future operating staff information needed to understand and optimally operate the systems. | Commissioning Agent |
| Construction | Verify and document that requirements for training operating personnel and building occupants are completed. | Commissioning Agent |
| Construction | This credit is a Construction Submittal and should be submitted at the end of the project. | OFS or LEED Consultant |
Design Intent and Sustainability Principles
The purpose of this credit is to provide for independent review of a building's mechanical, electrical and plumbing systems throughout the design process to ensure the most energy and water efficient methods for heating, cooling, and plumbing a building are operating as intended. A core aspect of the Harvard University Sustainability Principles hinges on continuous improvement in order to propel the university toward true sustainable building design and construction. Enhanced commissioning is a thorough process that ensures that Harvard's buildings will operate as effectively as they were designed. Enhanced commissioning is the demonstration of an institutional practice that promotes measures to increase efficiency.
Financial Considerations
As detailed in EA prerequisite 1: Fundamental Commissioning, commissioned buildings have much lower operating costs than buildings that are not commissioned. A study by the Davis Langdon group points out that pursuing Enhanced Commissioning does not cost much more ($1.00 to $2.00/SF) than what is required in Fundamental Commissioning (Matthiessen, Fay and Morris, 17). For the full cite, see Financial Links.
LEED Requirements (Construction Submittal)
See updated Credit Interpretation Rulings issued by the U.S. Green Building Council.
LEED-CI Version 3
"For all ENERGY STAR qualified equipment and appliances installed as part of the tenant's scope ofwork, achieve one of the following percentages (by rated power):
Percent Installed ENERGY STAR Qualified Equipment of ENERGY STAR Eligible Equipment |
Points |
|---|---|
70% |
1 |
77% |
2 |
84% |
3 |
90% |
4 |
This requirement applies to appliances, office equipment, electronics, and commercial food service equipment. Excluded are HVAC, lighting, and building envelope products."
- LEED 2009 for Commercial Interiors Rating System, page 21
LEED-CI Version 2.0
"In addition to the Fundamental Commissioning prerequisite, implement or have a contract in place to
implement the following additional commissioning process activities:
1. Designate an individual as the Commissioning Authority, independent of the firms represented on
the design and construction team, to lead the commissioning design review activities prior to the
end of Design Development.
2. Conduct a review of the tenant space’s energy-related systems contractor submittals.
3. Develop a single manual that contains the information required for re-commissioning the tenant
space’s energy related systems.
4. Verify that the requirements for training operating personnel and tenant space occupants are
completed. Have a contract in place to review tenant space operation with O&M staff and
occupants including a plan for resolution of outstanding commissioning-related issues 8 to 10
months after final acceptance."
- LEED-CI Version 2.0 Reference Guide, page 173
LEED Submittals
LEED-CI Version 3
- "Update the commissioning plan at milestones throughout the project. This should happen, at a minimum, during the design development phase, the construction documents phase, and just prior to the kick-off meeting with the general contractor.
- Prepare a systems list that indicates which systems have been included within the scope of enhanced commissioning.
- Request confirmation that the commissioning authority has documented experience on at least 2 building projects.
- Create a written schedule of building operator training.
- Retain a copy of the commissioning authority's design review, any designer responses to this review, and confirmation of the back-check.
- Retain copies of the owner's project requirements, basis of design, commissioning specifications, commissioning report, and systems manual."
- LEED-CI Version 3 Reference Guide, page 185
(Complete descriptions of documentation requirements are on LEED-Online)
LEED-CI Version 2.0
- "Provide the LEED-CI Letter Template, signed by the owner and independent Commissioning Authority, confirming that the required enhanced commissioning process requirements 1 and 2 have been successfully executed and that a contract for completing requirements 3 and 4 is in place."
- LEED-CI Version 2.0 Reference Guide, page 173
Additional Resources
EAc3: Measurement and Verification
EAc3 ROADMAP
| Design Phase | Recommended Approach: Activities | Recommended Approach: Responsibilities |
|---|---|---|
| Schematic Design | Establish Energy Cost Budget baseline building model. | MEP Engineers |
| Schematic Design | Establish a measurement and verification plan to determine the systems that will be monitored. | MEP Engineers |
| Construction Documents | Submit LEED documentation per EAc5 requirements. | MEP Engineers |
| Construction | This credit is part of the Construction Submittal and should be documented during this time. | MEP/OFS or LEED Consultant |
| Occupancy | Utilize the data from the measurement devices to evaluate energy conservation measures and occupant education for the life of the building. | Building Manager |
Design Intent and Sustainability Principles
Measurement and verification enables the building manager to evaluate how the various energy conservation measures implemented in the building perform once the building is occupied. Watt meters, air flow meters, duct pressure sensors all provide data that can be compared with the design case model. This re-evaluation not only helps to fine-tune design case models, but also assists the university in informing implementation of future technologies. The following three Sustainability Principles demonstrate the importance of measurement and verification to Harvard: a) “Developing planning tools to enable comparative analysis of sustainability implications and to support long-term economic, environmental and socially responsible decision-making,” b) “Encouraging environmental inquiry and institutional learning throughout the university community,” and c) “Establishing indicators for sustainability that will enable monitoring reporting and continuous improvement.”
Financial Considerations
Measurement and verification is essential in ensuring that systems are performing as designed. According to the David Langdon study, a good quality reporting system can add $2.00 to $4.00/SF to the cost of a project (Matthiessen, Fay and Morris, 17). For the full cite, see Financial Links.
LEED Requirements
See updated Credit Interpretation Rulings issued by the U.S. Green Building Council.
LEED-CI Version 3
"CASE 1. Projects Less than 75% of the Total Building Area
Complete 1 or more of the following:
- Install submetering equipment to measure and record energy use within the tenant space. (2 points)
- Negotiate a lease whereby energy costs are paid by the tenant and not included in the base rent. (3 points)
OR
CASE 2. Projects 75% of More of the Total Building Area
Install continuous metering equipment for the following end uses: (5 points)
- Lighting systems and controls.
- Constant and variable motor loads.
- Variable frequency drive operation.
- Chiller efficiency at variable loads (kW/ton).
- Cooling load.
- Air and water economizer and heat recovery cycles.
- Air distribution static pressures and ventilation air volumes.
- Boiler efficiencies.
- Building-related process energy systems and equipment.
- Indoor water riser and outdoor irrigation systems.
Develop and implement a measurement and verification (M&V) plan that incorporates the monitoring information from the above end uses and is consistent with Option B, C or D ofthe 2001 International Performance Measurement & Verification Protocol (IPMVP) Volume I: Concepts and Options for Determining Energy and Water Savings.
Provide a process for corrective action if the results of the M&V plan indicate that energy savings are not being achieved."
- LEED 2009 for Commercial Interiors Rating System, page 24-25
LEED-CI Version 2.0
"CASE A: For those projects with an area that constitute less than 75% of the total building area:
- Install sub-metering equipment to measure and record energy uses within the tenant space. (1 point.)
- Negotiate a lease where energy costs are paid by the tenant and not included in the base rent. (1 point)
OR
CASE B: For those projects with an area that constitutes 75% or more of the total building area, install continuous metering equipment for the following end-uses: (2 points)
- Lighting systems and controls
- Constant and variable motor loads
- Variable frequency drive (VFD) operation
- Chiller efficiency at variable loads (kW/ton)
- Cooling load
- Air and water economizer and heat recovery cycles
- Air distribution static pressures and ventilation air volumes
- Boiler efficiencies
- Building-related process energy systems and equipment
- Indoor water riser and outdoor irrigation systems
Develop a Measurement & Verification plan that incorporates the monitoring information from the above end-uses and is consistent with Option B, C or D of the 2001 International Performance Measurement & Verification Protocol (IPMVP) Volume I: Concepts and Options for Determining Energy and Water Savings."
- LEED-CI Version 2.0 Reference Guide, page 175
LEED Submittals (Construction Submittal)
LEED-CI Version 3
- "Develop an IPMVP-compliant measurement and verification plan, conforming to Option B, C, or D.
- For projects with an area less than 75% of the total building area, assemble documentation (e.g., lease agreements, utility bills) demonstrating that the tenant energy costs are paid by the tenant.
- Summarize the installed monitoring systems in the tenant space, demonstrating that, at a minimum, the required systems are monitored."
- LEED-CI Version 3 Reference Guide, page 193-194
(Complete descriptions of documentation requirements are on LEED-Online)
LEED-CI Version 2.0
- "For projects with an area that constitutes less than 75% of the total building area, provide the LEED-CI Letter Template, signed by a licensed engineer or other responsible party, describing the metering equipment installed for each end use, and/or indicating that energy costs are paid by the tenant and not included in the base rent, which must be confirmed by providing a copy of the applicable portion of the lease.
OR
- For projects with an area that constitutes 75% or more of the total building area, provide the LEED-CI Letter Template, signed by a licensed engineer or other responsible party, indicating that metering equipment has been installed for each end-use and declaring the option to be followed under IPMVP, 2001 version, plus provide a copy of the M&V plan following IPMVP, 2001 version, including an executive summary."
- LEED-CI Version 2.0 Reference Guide, page 175
Additional Resources
EAc4: Green Power
EAc4 ROADMAP
| Design Phase | Recommended Approach: Activities | Recommended Approach: Responsibilities |
|---|---|---|
| Budget Planning/CAPS | Harvard University holds a contract with Sterling Planet for purchase of wind energy for electricity usage. Project managers can take advantage of the negotiated price (see the CDs section below for details). | Client/Owner and CAPS |
| Schematic Design | Estimate the project's baseline electricity use to determine the amount of MWh to purchase in Renewable Energy Certificates (RECs). | Engineers |
| Construction Documents | When the Building Energy Model is complete, Harvard Project Managers can download the Purchase Order Agreement and fill it out for 2 years for 50-100% (min. 35% per LEED) of the energy load. Submit the signed form via fax (617-496-4763) to Joe Pendergast, Harvard Engineering & Utilities. | Project Manager |
| Construction Documents | Document EAc6 per LEED requirements. | Project Manager with OFS or LEED consultant |
| Occupancy | After two years, consider another contract to continue using RECs to offset the building's carbon emissions. | Client/Owner/Building Manager |
Design Intent and Sustainability Principles
Purchasing Renewable Energy Certificates for certified Green-e power decreases dependency on polluting, non-renewable energy resources. Green power applies to the first Sustainability Principle: Harvard University is committed to continuous improvement in demonstrating institutional practices that promote sustainability, including measures to increase efficiency and use of renewable resources." The sixth sustainable principle is that Harvard University is committed to establishing indicators for sustainability that will enable monitoring reporting and continuous improvement." Harvard's agreement for green power with Sterling Power, a green-e certified power provider, facilitates data collection for the university's Greenhouse Gas Inventory.
Financial Considerations
Harvard Project Managers have found the cost impact of the purchase of renewable energy certificates to be minimal. See the Sterling Planet Purchase Order Agreement for the range of options and costs.
LEED Requirements
See updated Credit Interpretation Rulings issued by the U.S. Green Building Council.
LEED-CI Version 3
"OPTION 1
Engage in at least a 2-year renewable energy contract to provide at least 50% of the tenant's electricity from
renewable sources, as defined by the Center for Resource Solutions' Green-e energy product certification requirements.
All purchases of green power must be based on the quantity of energy consumed, not the cost, as determined by the annual electricity consumption results of EACredit 1, Optimize Energy Performance.
OR
OPTION 2
Engage in at least a 2-year renewable energy contract to purchase at least 8 kilowatt hours per square foot per
year from renewable electricity sources as defined by the Center for Resource Solutions (CRS) Green-e Energy's
product certification requirements.
All purchases of green power must be based on the quantity of energy consumed, not the cost."
- LEED 2009 for Commercial Interiors Rating System, page 26
LEED-CI Version 2.0
"Provide at least 50% of the tenant’s electricity from renewable sources by engaging in at least a two-year renewable energy contract. Renewable sources are as defined by the Center for Resource Solutions (CRS) Green-e products certification requirements. Green power may be procured from a Green-e certified power marketer, a Green-e accredited utility program, or through Green-e Tradable Renewable Certificates, or from a supply that meets the Green-e Renewable Power definition."
- LEED-CI Version 2.0 Reference Guide, page 185
LEED Submittals (Construction Submittal)
LEED-CI Version 3
- "Maintain contractual documentation of the purchase of Green-e (or equivalent) certified renewable energy.
- If the certified renewable energy is purchased for the project by others, maintain documentation indicating that the renewable energy was retained on behalf of the project."
- LEED-CI Version 3 Reference Guide, page 201
(Complete descriptions of documentation requirements are on LEED-Online)
LEED-CI Version 2.0
"Provide the LEED-CI Letter Template, signed by the owner or other responsible party, documenting that the supplied power is equal to 50% of the project’s energy consumption and the sources meet the Green-e definition of renewable energy. Provide a copy of the two-year electric utility purchase contract for power generated from renewable sources."
- LEED-CI Version 2.0 Reference Guide, page 185
Additional Resources
Updated: Wednesday, August 5, 2009 5:21 PM


